AccAnalysisAccAnalysis
Enterprise IT & Cloud

Off the vendor's servers, onto infrastructure the client controls

The client's operational systems ran on servers controlled by a vendor, which meant limited control over infrastructure, data and release timing. We moved them to the client's own environments and automated the whole thing as code.

At a glance
Status
Delivered
Region
Germany
Engagement model
Dedicated team

Status: Delivered. Described from our own delivery records. Client identity, brand and commercial terms are withheld. Figures, where given, cover the period stated and nothing beyond it.

The organisation

Context

An organisation running its core operational systems on infrastructure owned and operated by its software vendor.

The arrangement was convenient until it wasn't: the client could not decide where its data lived, when its systems were updated, or how they were configured.

The brief

The problem

  • Hosting, and therefore the data, sat with the vendor.
  • Release timing and configuration were outside the client's control.
  • Moving away was hard by construction, which is what vendor lock-in means in practice.
  • There was no infrastructure definition the client owned, so the environment could not be reproduced elsewhere.
  • Deployment depended on the vendor's process rather than the client's.
The work

What we built

Migration of the production instances

To the client's own on-premises and cloud environments, running in parallel until each was proven.

Infrastructure as code

So the environment is a definition in the client's own repository rather than a configuration that exists only on a running server.

Automated deployment pipelines

So releases are the client's decision and a routine operation.

A container-based deployment

Moving from virtual-machine hosting to orchestrated containers, which is what made the environments portable.

Method

How we delivered it

  1. 1

    Inventory the existing environment

    What is running, how it is configured, and what depends on it. Much of this had never been written down.

  2. 2

    Build the target environments as code

    On-premises and in cloud, before moving anything.

  3. 3

    Migrate in parallel

    With the vendor-hosted system live until the new one was proven.

  4. 4

    Cut over

    With a tested path back.

  5. 5

    Hand over operations

    Runbooks, monitoring, backup and recovery, all owned by the client.

Sequence

How it was phased

PhaseDurationWhat happens
1Inventory & assessment
2–3 wks

Current environment documented, risks graded

2Target environments as code
3–4 wks

On-prem and cloud, containers, orchestration

3Pipelines
2–3 wks

Automated build, test and deployment

4Parallel migration
3–5 wks

Data and services moved, verified against the source

5Cutover & hand-over
2 wks

Switch-over, rollback tested, runbooks and monitoring

Indicative phasing for work of this shape. Actual duration varies with data quality, access and decision speed.

Hand-over

What the client keeps

  • Infrastructure definitions in their own repository
  • Deployment pipelines
  • Runbooks for every recurring operation
  • Monitoring and backup configuration
  • A tested recovery procedure
Stack
OdooDockerKubernetesTerraformPostgreSQLLinuxCI/CD